Before a Nevada prime contractor signs a construction contract, the owner must be informed of the provisions of NRS 108.245 in the statutory form, with a copy to each subcontractor (NRS 108.246) — a licensing duty, enforced through chapter 624. A 3-minute wizard becomes the form, submitted for certified mailing in minutes, with the proof archived permanently.
Statutory text pinned from leg.state.nv.us — cited on every document.
The provisions of NRS 108.245, a part of the mechanics' and materialmen's lien law of the State of Nevada, require, for your information and protection from hidden liens …
The timing, exactly
"Each prime contractor shall, before execution of a contract for construction, inform the owner with whom the prime contractor intends to contract of the provisions of NRS 108.245" (108.246(1)).
The statute says "inform" and names no method or mailing rule, so we recommend mailing five days before the last day — the calculator shows both dates.
Failure to inform owners and subcontractors "is a ground for disciplinary proceedings under chapter 624 of NRS" (108.246(3)) — the contractors' licensing chapter. No lien consequence in the pinned text.
Not sure where you stand? Run the free deadline calculator — enter the date you intend to sign and it cites each rule.
Who sends it, who gets it
The prime contractor — the party contracting directly with the owner (108.246(1)).
"The owner with whom the prime contractor intends to contract", and a copy to "each subcontractor who participates in the construction project" (108.246(1), (2)). Add the subs you already know; the rest are noted as copies to follow as they are engaged.
Subcontractors and suppliers send the NRS 108.245 notice of right to lien instead. The wizard will not sell you a notice you do not need.
How it works
Answer a short wizard
The gating question, you and your signer, the owner, the project, the date you intend to sign, and any subcontractors to copy — about 3 minutes. The document carries the 108.246 paragraph word for word.
We certified-mail every copy
Owner and subcontractor copies alike — submitted for certified mailing in minutes of payment, tracked end to end. You verify every address before paying.
Your evidence archive
The PDF, each certified tracking number, and a timestamped record of the deposit — the licensing-board answer to "did you inform the owner?" — kept on a permanent page.
Questions, answered straight
Who has to send the Nevada prime contractor's notice?
Under NRS 108.246(1), each prime contractor shall, before execution of a contract for construction, inform the owner with whom the prime contractor intends to contract of the provisions of NRS 108.245, in substantially the statutory form. Under 108.246(2) the prime also delivers a copy to each subcontractor who participates in the project. Whether that describes your job is a legal question we cannot answer.
When is it due?
Before execution of the contract for construction (NRS 108.246(1)). Enter the date you intend to sign and the calculator gives the last day before it, plus a mail-by date five days earlier — the statute says "inform" and names no method or mailing rule.
What happens if it is not given?
Failure to inform owners and subcontractors is a ground for disciplinary proceedings under chapter 624 of NRS, the contractors' licensing chapter (NRS 108.246(3)). The pinned text attaches no lien consequence.
Is this the notice of right to lien?
No. NRS 108.245's notice of right to lien is what subcontractors and suppliers deliver to the owner within 31 days of first furnishing — that is our Nevada Notice of Right to Lien product. This document is the prime contractor's advisory that such notices may arrive.
Is this legal advice?
No. NoticeSent is a document preparation and mailing service, not a law firm. We prepare and mail documents from the information you provide and give no advice or guarantees about outcomes.
The NRS 108.245 notice of right to lien — to the owner within 31 days of first furnishing, with the prime contractor's copy — for $39 flat.
Send the notice of right to lien — $39Run the calculator once per job and we'll email you before your mail-by date. No account; stop anytime.
Track a deadline freeThe duty is statutory. The proof should be too.
Before you sign. One flat $39, copies included.
Start your noticeMore for Nevada
- Nevada lien notices: the Notice of Right to Lien and the prime contractor's NRS 108.245 notice
Guide · quoted from the statute
- Notice of Right to Lien
$39 flat, certified-mailed · NRS 108.245