NoticeSent

Miss. Code Ann. § 85-7-407(2) — Mississippi notice to contractor service

Your Mississippi
30-day notice.
$39 flat, certified to the contractor.

A Mississippi sub-subcontractor or supplier with no contract with the contractor must give the contractor a written notice within thirty days of first delivery — or forfeit the lien (§ 85-7-407(2)). A 3-minute wizard becomes the notice with all four statutory items, submitted for certified mailing in minutes, with the proof archived permanently.

Statutory text pinned from the Legislature's enrolled acts — cited on every document.

Form NS-MS · specimenp. 1 of 1
NOTICE TO CONTRACTOR

(a) The name, address, and telephone number of the person providing labor, services or materials; (b) the name and address of each person at whose instance…

To (contractor)
Project and location
Description and value
Certified mail§ 85-7-407(2)
§ 1

The deadline, exactly

30 days

"Within thirty (30) days following the first delivery of labor, services or materials to the property, the person shall give a written notice to the contractor, or, if there is no contractor, to the owner" (§ 85-7-407(2)).

Mail early

"E-mail with a confirmed receipt, registered or certified mail, or statutory overnight delivery" (§ 85-7-407(2)) — the statute does not say whether mailing or receipt counts. The calculator shows a recommended mail-by date five days before day 30.

Forfeiture

A claimant who "fails to provide the required notice to the contractor … shall thereby forfeit his right to a lien under this article" (§ 85-7-407(2)). The pinned text has no late-notice cure. Send it on time.

Not sure where you stand? Run the free deadline calculator — it applies the rule to your first-delivery date and cites it.

§ 2

Who must be served, and who is exempt

The contractor

The party in privity with the owner (§ 85-7-401) — the only recipient when there is one. The owner is served only "if there is no contractor" (§ 85-7-407(2)).

Who gives it

Claimants with no privity of contract with the contractor — sub-subcontractors and suppliers to subcontractors — on other than single-family residential construction.

Who is exempt

First-tier subcontractors and suppliers in privity with the contractor (§ 85-7-401, § 85-7-407(2)); single-family residential construction (§ 85-7-407(4)). The wizard will not sell you a notice you do not need.

§ 3

How it works

01

Answer a short wizard

The situation check, the contractor, who ordered from you, the project and its location, what you furnish and its value if known, and your first-delivery date — about 3 minutes. The document prints each of the four items under its statutory heading.

02

We certified-mail the contractor

Submitted for certified mailing in minutes of payment. You verify the name and address before paying.

03

Your evidence archive

The PDF, the certified tracking number, and a timestamped record of the mailing — kept on a permanent page.

§ 4

Questions, answered straight

Who has to give the Mississippi § 85-7-407 notice?

Any person with a right to a lien under § 85-7-403 who does not have privity of contract with the contractor (or with the owner, if there is no contractor) — sub-subcontractors and suppliers to subcontractors. A first-tier subcontractor or a supplier to the contractor is in privity with the contractor and gives no notice under this subsection, and the section does not apply to single-family residential construction (§ 85-7-407(4)). Whether that describes your job is a legal question we cannot answer.

Who receives it, and when is it due?

The contractor — the party in privity with the owner — or the owner only if there is no contractor (§ 85-7-407(2)). It is due within thirty days following the first delivery of labor, services or materials to the property; a claimant who fails to give it forfeits the right to a lien. The statute states no mailbox rule for this notice, so we recommend mailing at least five days early.

What must it say?

Four items (§ 85-7-407(2)(a)–(d)): your name, address and telephone number; the name and address of each person at whose instance you are furnishing; the name and location of the project; and a description of the labor, services or materials with, if known, the contract price or anticipated value. There is no prescribed form or warning text; the notice prints each item under its statutory heading.

Is this legal advice?

No. NoticeSent is a document preparation and mailing service, not a law firm. We prepare and mail documents from the information you provide and give no advice or guarantees about outcomes.

What exactly do I get?

The notice with all four statutory items, USPS certified mailing with tracking to the contractor (or the owner), and a permanent archive page with a timestamped record of the mailing — for one flat $39.

Owner still not paying?

A Notice of Intent to Lien, generated and certified-mailed to the owner — and the contractor, if you choose — for $49 flat, any state.

Send a Notice of Intent to Lien — $49
Free deadline reminders

Run the 30-day calculator once per job and we'll email you 10, 5, and 2 days before the recommended mail-by date. No account; stop anytime.

Track a deadline free

The clock is statutory. The proof should be too.

30 days from first delivery. One flat $39.

Start your notice